This task has mostly stalled. Initial evaluations were done, but not recorded anywhere, and no follow-up was done. Thus, the first task is to re-gather the evaluations we previously had made.
One task that is currently in progress: acquire a newer Power system for ppc32/ppc64.
In order to get the work done that we need, we must make sure we have adequate hardware resources. Do we? What are the needs?
A rough proposed schedule for this project. When we anticipate that we will reach certain milestones. Also, if the project has an absolutely-must-be-completed-by date, mention it here.
| Milestone | Plan Date | Outlook | Comments |
|---|---|---|---|
| Re-gather the evaluations initially done. | 3/17/2008 | The task here is to figure out what we had planned before, and record it on this page in the comments. |
No resources have yet been dedicated, besides people's time.
List of people who are working on the project and their roles.
| Name | Role |
|---|---|
| Jeff Licquia | Project Owner |
Tasks will map many-to-one to milestones. Tasks are specific actionable work items that need to be completed in order to reach a milestone
| Task | Owner | Status | Outlook |
|---|---|---|---|
| Gather previously collected data. | Jeff Licquia | In progress. | |
| Acquire a newer Power-based system. | Theodore Ts'o | In progress. | Last word: working with George Kraft and Kay Tate on this. |
| Task | Owner | Status | Outlook |
|---|
Tasks that can't be scheduled yet because they are waiting on some other task or external entity
| Task | Owner | Status | Outlook |
|---|
The one thing we know about, so far, is that we most probably need a better/newer Power system than the PowerMac we have. Ted is working with some people at IBM to see if we can get one contributed.